28.05.2024
Outage campaign 2024: Energoatom connected a 1,000 MW unit to the grid after outage
On May 27, 2024, at 03:05 p.m., the Energoatom 1,000 MW power unit was connected to the power grid. Its capacity is currently ascending.
Thanks to the prompt actions of the Ukrainian nuclear employees, the outage was completed three days ahead of schedule.
As a result, additional 1,000 MW of electricity strengthened the Unified power system of Ukraine.
Head of Energoatom Petro Kotin emphasized: “Ukrainian nuclear employees will continue to make maximum efforts to shorten the period of outage, so that all our power units work at maximum capacity. In conditions when the enemy is destroying the Ukrainian energy infrastructure, our task is to hold the energy front."
Energoatom works for Ukraine and Ukrainians!
MORE NEWS
The Rivne NPP was visited by the Norwegian delegation led by Minister of Foreign Affairs Espen Barth Eide
22.10.2024
Nuclear has been providing up to 70% of Ukraine’s energy
21.10.2024
Sweden will continue to support the Ukrainian energy industry
21.10.2024
Development and protection of domestic nuclear power plants are crucial aspects for the functioning of the entire country
21.10.2024