Petro Kotin inspected works on the completion of the Khmelnytskyy NPP unit 3
On February 16, 2023, during a working visit to the Khmelnytskyy nuclear power plant, President of SE "NNEGC "Energoatom" Petro Kotin inspected the progress of works on the completion of power unit 3.
Currently, at the KhNPP-3, a roof has already been installed, heating has been carried out, and cleaning and painting works are underway. Soon, Energoatom will be ready to start installing the equipment.